Not too much to report after the third week. The framing and rebar for the foundation has been laid. The screw up by the engineer is on its way to being fixed and we’re able to move ahead with plans. Hopefully the inspection will happen on Tuesday this week and the concrete will begin pouring on Wednesday. We were able to get rid of about half our dirt, but still have plenty if you need it!